Factory Capacity & Layout Audit Pro
Turn factory data into a bottleneck, capacity, and layout-risk decision. #التجارة
Factory Capacity & Layout Audit Pro
Turn factory, warehouse, assembly-line, or packing data into a clear expansion decision.
Provide station cycle times, staffing, daily demand, and optional material-flow data. Get a decision-ready audit that identifies the true bottleneck, required capacity, and layout risks before you add labor, equipment, or floor space.
中文样例:峰值日要出 1,200 箱,加人还是加装盒位?
以下为模拟数据。水果包装线每班有效作业 360 分钟,分拣、装盒、封箱分别用时 15、20、12 秒/箱。
| 方案 | 每班理论上限 | 与 1,200 箱目标相比 |
|---|---|---|
| 每道工序各一个工位 | 1,080 箱 | 缺 120 箱 |
| 装盒位增加一名帮手,节拍仍为 20 秒/箱 | 1,080 箱 | 缺 120 箱 |
| 两人各用一个独立装盒位,供料充足 | 1,440 箱 | 余 240 箱 |
原线的瓶颈在装盒。若单个装盒位能稳定达到 18 秒/箱,360 分钟恰好可装 1,200 箱。增加第二个独立装盒位后,瓶颈转到分拣。实际可承诺产量还要核对停机、返工和供料记录。
下载包内附三组 CSV,可用自己的工序节拍和需求量复算。
What you get
- Peak-day and P90 demand analysis
- Station-by-station capacity calculation
- Bottleneck ranking by utilization
- Required number of parallel stations
- Daily capacity gap and expansion decision
- Buffer-sizing checks
- Material travel-distance analysis
- Pedestrian / forklift aisle-crossing warnings
- A concise management-ready Markdown report
Best for
- Factory managers planning a new workstation
- Warehouse and packing operations with missed delivery targets
- Assembly lines with uncertain bottlenecks
- Operations consultants preparing a capacity review
- Teams deciding whether to add people, equipment, shifts, or floor space
How it works
Provide three simple CSV files:
stations.csv— cycle time, parallel stations, operators, uptime, and queue targetdemand.csv— daily production demandflows.csv— optional distances, buffers, and aisle conflicts
Run the included audit script.
Receive:
ADD_CAPACITY,MANAGE_RISK, orCAPACITY_OK- the current bottleneck
- the number of parallel stations required at peak demand
- the next bottleneck to protect after expansion
- layout actions ranked by severity
Example decision
Decision: ADD_CAPACITY
Packing is operating at 123% utilization on peak demand and requires 2 parallel stations instead of 1. Before adding the station, resolve the undersized buffer and the forklift/pedestrian aisle crossing between assembly and packing.
Included files
- Reusable
SKILL.mdworkflow - Python capacity and layout-risk audit tool
- Ready-to-edit CSV templates
- Input schema reference
- Example data and automated test
Requirements
- Python 3.8 or newer
- No external Python packages
- Runs locally and works offline
- No API key or paid service required
Important note
This tool provides an operational screening audit. It does not replace detailed engineering, safety, fire-code, ergonomic, or regulatory review.